MERALCO serves growing power needs in parts of Laguna and Batangas

Must read

Manuel V. Pangilinan-led Manila Electric Company (Meralco) upgraded its Calamba 230 kilovolt (kV) -115 kV Delivery Point Substation to enhance the reliability and stability of electricity service in parts of Laguna and Batangas.

The project involved the installation of a third 300 megavolt ampere (MVA) power transformer, as well as associated 115 kV and 230 kV Gas Circuit Breakers, and protection and control panels.

This upgrade will support the growing power demand of key establishments including SM City Calamba, SM City Sto. Tomas, Mariwasa-Siam Ceramics Inc., Calamba Doctor’s Hospital, Philippine Manufacturing Co. of MURATA Inc., STMicroelectronics Inc., and Samsung Electro-Mechanics Philippines Corporation, as well as the neighboring communities in the area.

As part of its commitment to delivering high-quality, stable and reliable service, Meralco continues to invest heavily in upgrading and modernizing its electricity distribution system.|

- Advertisement -spot_imgspot_imgspot_imgspot_img

More articles

I have lived in Lipa City long enough to know where the boundary lies between quiet mornings and a string of incidents that unsettles...
MALVAR, Batangas — The Municipality of Malvar is positioning itself as an emerging model for sustainable local governance after forging a waste-to-energy partnership with...
BATANGAS CITY — Authorities are set to file criminal charges on February 3, 2026, against individuals behind the ₱1.1-billion illegal cigarette seizure in Batangas...
- Advertisement -spot_img

Latest article

- Advertisement -spot_img